ToW 5-Year Road Plan 2023-2018
Town of Washburn 5-Year Road Plan 2023-2028
Based on May 22, 2023 Road Inspection Tour
The following road categories, (unless otherwise listed), are listed according to priority.
Funding and other factors could change the order of priority within the categories as discernment from the Town Board directs within the 5-year timeframe.
Paved Roads
- South Maple Hill (Repaved 1/3 Mile in 2022): Gravel Shoulders Application.
- Wannebo Road from Chequamegon Heights to Ondossagon- 2 miles, repave, add shoulders (BIL grant).
- Double Chip seal on Engoe Road, from the intersection of Engoe/Viater Rd, 1 mile west to Brevak Road.
- McKinley Road from Badura’s corner to Ondossagon Road-2 miles, chip seal.
- Ondossagon Road from McKinley to Wannebo- ½ mile wedging and chip seal.
- Paulson Road from Church Corner Road to South Maple Hill Road – asphalt overlay
- Engoe from Ondossagon to Bjork Road-Chip seal/double layer.
- Nevers Road from top of hill to dairy – pulverize and overlay.
- North Maple Hill Road – pulverize and overlay sections.
Dead End Roads
- Scholl Road at the end of road-pulverize and pave.
- Ondossagon Road from McKinley to the north- cut out and patch bad spots, pulverize end.
- Pajala Road-Culverts.
Gravel Roads
- North Church Corner- .9 miles culvert sleeve and gravel.
- West Maple Hill- 1 mile ditch and pave.
- Rustic Road-.4 miles gravel.
- Sky Road-gravel.
Forest Service Roads
- 251-pulverize and repave 1 mile, RAC grant.
- 251-gravel from 236 going east with $100,000 worth of gravel RAC grant.
- Broken Rock- Contract with Forest Service.
Yearly Crack Seal Maintenance (5-year goal: 15 – 18 Road Miles)
- Nevers Road.
- Ondossagon Road.