June 1, 1982

Met with Tony Wilhelm of Wilhelm Engineering concerning bridge on Four Mile Creek, Discussed total costs and what it would actually cost the town. Estimated total cost at 115 to 140 thousand. Town’s costs up to $30,000.00 of wh1ch $12,600.00 are engineer costs.

Philip E. Tetzner

 